I've attended many pre-job meetings that the GC stated "Requests for Information will have a response within a day". My usual action was to send as many RFI's as I could immediately to clear up discrepancies (better proactive than reactive) before they became problems. They've rarely been answered within a week; some have taken months.

There have been a few occasions where I've submitted alternate lighting/switchgear packages, only to be told "No substitutions, go strictly by the specs". The same people have asked me to value engineer the job halfway through, probably after some "bean counter" actually counted up the "beans".
You can always tell a job's gonna be a Turkey when it sounds like they've got delusions of grandeur