Just wondering how you guys might tackle this. I am doing the build outs on a few retail stores in a new strip center. We start a sunglass hut tomorrow.

Here's the question. CG that handled the erection and exterior work of the structure had an EC run the pipe for service laterals back to the xmfmr pads. All lateral pipes are 4" EPVC. Well all our services are only 200A and POCO requires us to use their can which only goes to 2.5" on the bottom KO's.

I wont go into how bad the pipes are out of plumb... it's a real mess.

I have seen this done with PVC (water pipe) reducing bushings and it looks like a hack job. Any advice on how to get from 4" to 2.5" and have it look respectable?