Gentlemen I have been reading everyone's comments for a few years now but finally broke down to post a question to seek your input on a job.

My local inspector has required me to tie a new service ground into the rebar of the footings of the addition I am doing. My questions is with a 200A 120/240V service do I still need the ground rods or does the connection to the footings offset the need. I was intending on still adding the rods but then I questioned myself if I would be creating a bigger problem by doing so. Any advice is appreciated.

Thanks
Pat