hello to the group. I have been assigned as foreman for a corporate office building. The building is going to be constructed of Tilt Up Panels that are built on site on top of the slab. The panels will be the finished interior walls of the building thus I have 78 boxes and related piping to install into these panels.

I am looking for suggestions, hints, or recommendations from those of you that have delt with these types of panels before. I need help mainly in the methods that you used to secure your raceway piping and boxes to the panels to hold them plumb and level to the finished side of the panel face.

Any help would be great appreciated. You may leave your comments here or if you wish email me directly at k0pwo@comcast.net

Thanks for your time.