hi
thank you all for the help about testing circuits , yes Im familiarized with lock out/tag out and Its a good way to work safely.
Ok my question now is aobut panels divided by sections . I have a panel that is divided in 3 sections , like you know the code says that we can have 42 breakers per panels (100 amps main feeds 120 V receiptacles),my question is :If I have some of the circuits that belong to the first section piped to the the second section (they mis-laidout in the slab)and I need to bring these circuits to the first section panel can I use the 2" nipple that I have between the first and second section for my feeders to pull my circuits ? or I need another nipple just for branches besides this nipple to feed the second section? is there any article in the code about this?
Thank you