earlydean wrote
Quote
You intend to do an upgrade without notifying the PoCo about it?

Here, the AHJ notifies the Poco after inspection & then the poco decides if they want to change their feeders... Alot of areas here have oversized feeders already installed for future upgrades (one house had 4/0 CU feeding a 100A panel!) most poco's here will allow a 200A panel to exist on 1/0 AL XPF type feeders underground.. Another poco wants a 3" conduit for 200A underground! & then they pull 1/0's... Little overkill for the wire size???

If the AHJ doesnt call the poco for you, you should let them know so they can evaluate their feeders for your intended upgrade... I'm just used to not having to worry about it! [Linked Image]

-Randy