Medium-voltage gear/cables have their own set of concerns.
  • Unique owner/facility requirements
    More interest/details by utility/AHJ than with <600V
    Splice/termination workmanship/quality
    Differing cable specs/construction… industrial versus utility
    Cable overvoltage-testing procedures
    Installation/installed cable radius
    Cable-shield configuration/layout
    Grounding electrode arrangement and size typically significantly greater than for <600v work
It may be possible to “farm out” splicing/termination labor to a specially contractor. [sparky*62 — Apologies for the delayed response.]