When you are working with CMU construction with the conduit in the wall, how much time do you expect to spend with the bricklayers?

I lay out all opening clearly on the bottom course or footing. We assemble the boxes with 3' conduit stubs, etc.

I can't place the boxes for them. Yet it seems that they expect someone onsite at all times. Usually at this stage of the project there is not enough other work to be done to stay busy so I end up babysitting the bricklayers.

I just got back from a trip to the jobsite on this beautiful saturday morning and I'll have to go back again this afternoon. Maybe I just need to vent......but over the years bricklayers as a group are the most difficult trade to work with.