Underground feeders failed on a 5 unit apartment building. There was no disconnect on the original install.

We are running the new conductors around the outside of the building, in emt pipe. We will be penetrating the wall to enter the meter room, run about 20' inside the meter room to the jbox where we tap and feed each panel. Everything ran in EMT.

My question is do I need a fused disconnect where I enter the this building?

Last edited by Trick440; 10/24/14 01:08 AM.

Shake n Bake