hmm, well i never really liked the idea of gfci's anywhere near the weather. Maybe i've seen a little too much abuse, incidents where the line side could be compromised, missing covers, etc.

Usually, i'll start a 'rough out' with a service gfci under , or near the panel. I'll make single runs back to that gfci to all the non-dedicated gfci's. That way they can be parsed out into dedicated circuits in the future.

That's paid off a number of times for me on those 'don't know what i'm building 'til i get there'jobs i've had the good fortune to step into...