The GEC is connected to the top of the main switch through that LB.
The other conduits at the bottom of the gutter include a 4inch conduit underground for a feeder to a proposed detached shed on the property.
The smaller 1 and 1/4 conduit at the bottom of the gutter goes to the parking lot pole lights.