In central florida. I am trying to get some idea of the going rate, I have heard anything from $5.00 per sq ft to 10% of the overall building cost. I estimated materials to cost me around $4,000. It's a 4 bed, 2200 sq foot house. About 13 recess cans thruout. I bid about 12,000 and was told by the builder the bids he already had were between 6000 and 7500. That sounds way off to me. Do you think the builder is getting legitimate bids in that area, do you think my bids are that far off and that uncompetitive?

I have only got licensed this year, and I have never really dealt with any pricing or cost issues previously in my career while working with others. I've always worked for companies that didn't share cost info or budget info.

I'm trying to learn as I go, run my little operation in my free time while still working full time for another company. Until I can afford to support myself fulltime with leads and service work to pay the bills.