Also I need some lock-dogs that fit BKM breakers.
I wish that there was a lock-dog that fitted all breakers.
I have no idea why the company went with a Bremca Main Switchboard, I would have installed a Vynco board given the choice.
The electrical company low-balled on the install, I think.
Good CT chamber, but the distribution chambers are a bloody mess.
I've organised a 2 day shut-down to correct a number of issues the least being cables being bought into the board without glands and sharp edges surrounding the cables. [Linked Image]
Since I have taken over as Maintainence Supervisor, I have a whole list of things that have to be done while the power is off.
At last count, I had 260 things to be fixed to save peoples lives alone, that is without the operational stuff that needs fixing.
Don't ever get into the newspaper industry folks, it will take years off of your life.