Bidding a job with an older exisiting 480-277/208-120, 112.5 kva transformer is to be used. The specs. ask for a field test to be performed to see if the xfrmr is functionig properly before submitting a bid. Problem is there is no power to the building. Is there anyway to test the unit without powering it up??
Thanx, John.